|
TANJUNG BIN POWER PLANT
(3x700 MW)
Malaysia
Malaysia's
2100 MW Tanjung Bin coal-fired plant is one of the largest
infrastructure projects currently under development in south-east Asia
The RM7.8 billion coal-fired power plant to be built by Tanjung Bin
Power Sdn. Bhd. is among the largest of the infrastructure projects
currently under construction in the nation. As a privatised project
under the IPP programme, it ranks as the biggest capacity todate. The
project involves developing, designing, manufacturing, constructing,
testing, commissioning, operating and maintaining a 2,100MW coal-fired
power plant for a period of 25 years from the day the first of the three
power generation unit achieves commercial operations.
The
Tanjung Bin Power Plant, built on an abandoned aquaculture
farm, is located in Mukim Serkat, Pontian, adjacent to the mouth of
Sungai Pulai in south-western Johor. It overlooks the Port of Tanjung
Pelepas. When commissioned, the power plant will offer low-cost base
load energy to the nation. The plant is expected to play a key role in
realising the government’s plans for transforming south-west Johor into
a new growth area.
The
plant will be a conventionally-designed, pulverised coal-fired power
plant consisting of three 700MW sub-critical boilers and tandem
compounded-type turbine generator units. It will utilise proven coal
combustion technology that is safe and efficient. State-of-the-art,
clean coal technology will treat emissions to meet the requirements
stipulated in the Environmental Impact Assessment approved by the
Department of Environment, Ministry of Natural Resources and
Environment. The use of coal as fuel is in line with the government’s
aspiration to reduce dependency on natural gas, from which close to 70%
of the country’s power is generated currently.
Covering about a third of its entire 900-acre site, the Tanjung Bin
Power Plant-in addition to its boilers and steam turbine generators-will
be built with a coal unloading jetty, coal handling and storage
facilities, and an ash disposal pond, among others. Electrostatic
precipitators will limit particulate matter in the emissions, which will
be further scrubbed clean by a flue gas desulphurisation process before
being discharged to the atmosphere through a 200-metre high chimney.
The
facility’s proximity to the sea will provide it with a source of cooling
water as well as furnishing it with a suitable means for the delivery of
fuel. Coal will be imported through bulk carriers from mines in
Indonesia, China, Australia, South Africa, and elsewhere as the need
arises. The electricity generated will be transmitted from the plant’s
electrical switchyard to the power grid of the national utility, TNB,
via extra high-voltage 500kV transmission lines. The power will be sold
to TNB under the terms of the Power Purchase Agreement executed on 25
July 2002.
The ground-breaking ceremony of the Tanjung Bin Power Plant was
performed by the Menteri Besar of Johor, YB Datuk Abdul Ghani bin
Othman, on 19 January 2004. As of end November 2004, almost all piling
works s have been completed and overall construction works about 30%
have been completed and we are on track to meet the scheduled dates. The
Commercial Operation Date of the first unit is scheduled for 31 August
2006. The second unit will follow six months after that, in February
2007, while the third and final unit is expected to be commissioned
another six months after the second, i.e. by 31 August 2007.
|